Impact window lead times: ES Windows, ESR and Mr. Glass
As last confirmed November 11, 2026, made-to-order impact windows typically take 6 to 9 weeks (ES Windows (ESW)) or 8 to 12 weeks (Mr. Glass) to manufacture, and 6 to 9 weeks for the ESR series. Those are factory windows that start when an order is confirmed — not delivery dates. This page keeps the current numbers with their date, explains what sits around them, and logs every change so you can see when a window moved.
Last checked: October 17, 2026 · These are manufacturing windows, not delivery dates: they start when an order is confirmed, and measurement, permitting and installation scheduling sit outside them. Your specific window is confirmed during project review. Last confirmed November 11, 2026; a window that has aged is not a cautious estimate, so it carries its date.
Current manufacturing windows
| Manufacturer | Line | Typical manufacturing window | Expedited |
|---|---|---|---|
| ES Windows (ESW) | All configurable lines | 6 to 9 weeks | Not published; ask at review |
| ES Windows (ESW) | ESR series | 6 to 9 weeks | 2 to 3 weeks, for an additional charge |
| Mr. Glass | All configurable lines | 8 to 12 weeks | Not published; ask at review |
Last confirmed November 11, 2026. These windows were provided and approved for publication by SmartWay’s owner; they are not copied from a manufacturer document. Only brands the Builder can configure are listed: publishing a window for a brand you cannot select would promise availability we do not offer.
What the window covers, and what sits around it
A lead time answers one question: once the order is confirmed, how long does the factory take to build it? Everything else in a project happens before or after that window:
- Before: building the project, specialist review of sizes, product fit and approvals, professional measurement on installed projects, and the permit application. Final sizes have to be settled before the order can be confirmed.
- During: the manufacturing window in the table above.
- After: delivery by UPS or freight carrier, confirmed for each address during review, then installation scheduling and the inspections.
That is why a lead-time table cannot become a delivery date. Two homeowners with the same window line can see very different total timelines because their permits, measurements and delivery addresses differ.
What moves a lead time
These are the questions to ask when your window is confirmed at review. They are general causes, not measured effects for any line:
- When the order is really confirmed. An open size question, a missing configuration detail or an approval that does not cover your size delays the start of the window, not its length.
- Changes after confirmation. A new size or color after the order is placed can send it back to the start.
- Options. Finishes, glass makeups and hardware choices are made to order; ask whether yours affects the schedule.
- Factory demand. Backlog at the plant changes over the year, outside anything a buyer controls; it is the main reason the numbers here carry a date.
- Expedited production. Published only for the ESR series, for an additional charge.
How to read a lead time on any quote
Whoever you buy from, a lead time is only useful when you know what it measures. Five questions make any number comparable:
- When does the clock start? At deposit, at signed drawings or at a confirmed factory order are three different dates.
- Which unit? Windows are quoted in days or weeks, as each manufacturer gives them; the table above keeps the unit it was given in. Ask whether days are calendar or business days.
- Does it include delivery? A manufacturing window ends when the product is built, not when it reaches your driveway.
- What resets it? Ask what happens if a size, color or glass changes after the order is confirmed.
- How old is the number? A lead time without a date cannot be checked. Ours carries November 11, 2026 and the change log below.
Ordering around hurricane season
The Atlantic hurricane season runs from June 1 to November 30. Openings protected by impact glass need no shutters to put up, but only once they are installed — so the useful question is when to start, not when to order:
- Start early. Count back from June 1 through installation, delivery, the manufacturing window, the permit and review. A fall or winter start leaves slack for each step.
- Mind the code change. The Florida Building Code, 9th Edition (2026), takes effect December 31, 2026. Miami-Dade’s notice says permit applications and plans submitted on or after that date must comply with it. Approvals are being updated to match: the ES Windows NOA we read for our NOA guide carries a statement of conformance with both the 2023 and 2026 editions.
- Do not let urgency skip review. A rushed size or the wrong approval costs more time than it saves. The permits and inspections guide covers the permit side.
Change log
Every change to the published windows is added here with its date, newest last. A window that has aged is not a cautious estimate, so the history stays visible.
| Confirmed | Change | Windows published |
|---|---|---|
| August 24, 2026 | First published: typical manufacturing windows for ES Windows (ESW), its ESR series and Mr. Glass, confirmed by the owner. | ES Windows (ESW): 40 to 50 days; ESR series: 5 to 7 weeks (expedited 2 to 3 weeks) · Mr. Glass: 8 to 12 weeks |
| November 11, 2026 | ES Windows (ESW) and its ESR series moved to 6 to 9 weeks; ESR expedited production stays at 2 to 3 weeks and Mr. Glass stays at 8 to 12 weeks. Confirmed by the owner. | ES Windows (ESW): 6 to 9 weeks; ESR series: 6 to 9 weeks (expedited 2 to 3 weeks) · Mr. Glass: 8 to 12 weeks |
Source of record: SmartWay’s owner (owner confirmation), verified November 11, 2026. Not a manufacturer document.
Questions we actually get
How long do impact windows take to make?
What is the ES Windows (ESW) lead time?
What is the Mr. Glass lead time?
Is the lead time the date my windows arrive?
When should I order impact windows before hurricane season?
Sources
- SmartWay manufacturing windows — owner confirmation recorded in the site’s lead-time data, verified November 11, 2026
- Miami-Dade County — Florida Building Code 9th Edition code change notice (effective December 31, 2026)
- Miami-Dade NOA No. 26-0729.15 — ES Windows, LLC; statement of conformance with FBC 9th Edition (2026) and 8th Edition (2023), dated July 24, 2026; expires July 20, 2027
- NOAA National Hurricane Center — tropical cyclone climatology (Atlantic season June 1 to November 30)
Last checked: October 17, 2026. The table and the change log are generated from the site’s lead-time record at build time, so they cannot drift from the brand pages.