Guides · The process
Do you need a permit to replace windows in Florida?
Short answer: yes. Replacing window or door assemblies is permitted work under the Florida Building Code; repairing a broken pane in an existing frame generally is not. The permit is the proof, and here is how the process really works.
An impact window’s approval belongs to a tested assembly installed a specific way. The permit and its inspections are the only mechanism that verifies yours was. That makes the permit file — not the brochure — the document that protects your money, your insurance credit and your resale. Here is the process end to end, with the statute numbers most pages get wrong.
Yes, it needs a permit — and who pulls it matters
Replacing window or door assemblies is permitted work under the Florida Building Code. Repairing a broken pane in an existing frame generally is not — the line is whether the tested assembly itself is being installed. In practice, the contractor of record pulls the permit for your project, and that is the arrangement that keeps responsibility where it belongs.
Florida also has an owner-builder exemption: a homeowner can pull their own permit for their own residence. Read the disclosure it requires before getting excited — the owner takes on direct, onsite supervision of the work, selling or leasing within one year after completion creates a statutory presumption that the work was undertaken for sale or lease (s. 489.103, F.S.) — which is what puts the exemption in question — and none of a contractor’s obligations protect you from yourself. For made-to-measure structural assemblies in a hurricane zone, it is rarely the bargain it looks like. The full walk-through is in owner-builder permits for impact windows.
Either way, verify whoever contracts the work holds the right state license: the Florida DBPR’s license verification portal shows status, scope and discipline history. Unlicensed activity is a crime in Florida — a more serious one during declared emergencies — and the state runs a hotline for reporting it.
What goes into the permit package
Details vary by city and county (most South Florida cities run their own building departments), but a window-replacement package consistently includes:
- the permit application with the job’s total value;
- a floor plan or elevation drawing showing each opening being replaced — its location, size and what goes in it;
- the product approval documents — Miami-Dade NOAs or Florida Product Approvals — for every product in the job (this is where the approval numbers you learned to look up become mandatory paperwork, and knowing how to read a Miami-Dade NOA lets you check each one covers its opening);
- a schedule tying each opening to its product, its approval number and its design pressures;
- contractor license and insurance documentation, and fees.
Taller buildings carry extra requirements — site-specific engineering is generally mandatory above thirty feet, and threshold buildings add special-inspector paperwork. Condo and HOA projects need association approval on top of the public permit, and associations often constrain appearance choices; get that in writing before anything is ordered.
How it works in Broward, Miami-Dade and Palm Beach
The permit is issued by whichever building department has jurisdiction over your address — a city with its own building department, or the county where the county is the permitting authority. The county requirements below are the baseline the city checklists build on; always use the checklist of the office that will issue your permit.
Broward County
Broward runs on a shared form set. The Broward County Uniform Building Permit Application carries the job value and, in capitals, the warning that a Notice of Commencement must be recorded and posted on the job site before the first inspection. Each replaced opening goes on the Uniform Retrofit Window & Door Schedule — Board of Rules and Appeals (BORA) Policy 20-01 — which lines up, per opening, the product acceptance number, the pressure rating in the product approval, the design pressure the opening requires, its size and wind zone, and whether the glazing is impact.
For houses and townhouses with a roof height up to thirty feet, BORA Formal Interpretation #24 accepts the required design pressure from a sealed site-specific plan, from a plan with a sealed worst-case pressure chart, or from the county’s Fenestration Voluntary Wind Load Chart. Above thirty feet, a site-specific design sealed by a Florida engineer or architect is required, and a generic chart is not accepted. Where the county itself is the permitting authority, applications go through Broward County’s online ePermits system.
Miami-Dade County
Miami-Dade’s Department of Regulatory and Economic Resources lists replacement windows, mullions and glass doors under permit categories 82 and 83, and exterior doors without glass under category 104. Three items are required, and an incomplete package is not accepted: the building permit application, a contact sheet, and an elevation drawing of each exterior wall with replaced openings, showing their sizes and product approval numbers (Miami-Dade or Florida Building Commission). The current NOA for each window, glass door or mullion goes with it, and mullion cross-sections are shown where mullions are used. Contractors submit through the county’s E-Permitting portal, and inspections are scheduled and tracked online. In threshold buildings — more than three stories or more than fifty feet tall — window and door installation also needs a threshold inspection by a special inspector.
Palm Beach County
The county’s Planning, Zoning and Building Department runs permits through ePZB: register, open Building → Online Submittal, upload the application and drawings as PDFs, and pay online once the review is done. Inspections are scheduled and tracked in the same portal, which on inspection day shows the assigned inspector and the day’s itinerary. The county’s list of work that needs no permit includes repairing a window within its existing frame below a small value limit — replacing the window is not on that list.
A note on Miramar
Miramar issues its own permits through the City of Miramar Building Division(Building, Planning & Zoning Department, 2200 Civic Center Place, Miramar, FL 33025, 954-602-3200), and its Windows & Doors Application Package shows how a Broward city builds on the county forms. Registered contractors apply for residential and commercial work; owner-builders may apply for residential work only, with photo ID matching the address, proof of ownership and homestead verification — and if a contractor is hired, the contractor must pull the permit. The package asks for a cost breakdown, a floor-plan sketch with every opening numbered to the Broward uniform schedule, current Florida Product Approvals or Miami-Dade NOAs with the applicable options circled, the Broward wind load chart (or sealed calculations), an HOA awareness affidavit even when there is no HOA, and a debris-removal affidavit. Documents can be submitted through the Building Division’s online service.
The Notice of Commencement — where the internet is out of date
Florida’s lien law requires a Notice of Commencement (NOC) to be recorded with the county and posted at the job site before the first inspection, for direct contracts greater than five thousand dollars (s. 713.135, Florida Statutes). That threshold was raised effective October 1, 2023— a large share of pages ranking for this topic still quote the old, lower figure. Practical points:
- Most whole-home impact projects clear the threshold, so plan on an NOC;
- it is recorded with the county clerk, and a copy must be posted at the site — the first inspection does not happen without it;
- under s. 713.13 it is recorded before work actually starts, it becomes void if work does not begin within 90 days of recording, and by default it runs for one year unless the notice states a longer period;
- the NOC is also the anchor of the lien-law paper trail that protects you from paying twice — releases of lien and the final payment affidavit, covered in our quote comparison guide.
What the inspections actually verify
Expect at least an in-progress and a final inspection, and expect the inspector to look at exactly the things that make the approval real:
- Anchors: type, spacing and embedment matching the approval’s installation instructions — the schedule on the drawings, not someone’s habit;
- Bucks and attachment: the wood or structural bucks the frame fastens to, and how they connect to the wall;
- Labels: the permanent markings on the glass and frame that match the product to its approval — do not peel anything off before the final inspection;
- Sealing and flashing: the waterproofing details around the opening;
- Egress: that sleeping rooms keep a usable emergency exit (see bedroom egress rules).
When the final inspection passes, the permit closes — and that closed permit is the durable, public evidence that your protection is what the paperwork says it is. Keep a copy of everything; it feeds directly into the wind mitigation credit.
Skipping the permit: how it surfaces later
- During the work: stop-work orders, fines, and in the worst case removal of finished work so it can be inspected;
- At claim time: protection you cannot document is protection your insurer may not credit — unverified openings classify as unverified on the wind mitigation form;
- At resale: open permits and unpermitted alterations show up in due diligence, and buyers price them like problems, because they are. After-the-fact permits exist, and they are the expensive version of doing it right.
Questions we actually get
Is a permit really required just to replace windows?
Can I get a permit after the windows are already installed?
Do condo units need a permit for window replacement?
How do I check that my contractor’s permit was actually closed?
Where do I get a window replacement permit in Miramar?
Does an older house have to bring every window up to current code at once?
Sources
- Florida Statutes §713.135 — Notice of Commencement filing threshold
- Florida Statutes §489.103 — owner-builder exemption: onsite supervision, and the one-year sale-or-lease presumption and §713.13 — recording and posting requirements
- Miami-Dade County — window, shutter and door permit requirements (categories 82, 83 and 104; E-Permitting; threshold inspections) and Notice of Commencement guidance
- Broward County — window/door replacement application packet and the county’s ePermits system
- City of Miramar Building Division — Windows & Doors Application Package (rev. 12/2024), which reproduces the Broward County Uniform Building Permit Application (rev. 11-17-2022), BORA Policy 20-01 (Uniform Retrofit Window & Door Schedule) and BORA Formal Interpretation #24 (January 9, 2025)
- Palm Beach County Building Division — Building Division home and ePZB links, how to register and apply in ePZB, ePZB inspection information guide and items not requiring a permit
- Florida Existing Building Code §707.4 — replacement windows and doors
- Florida DBPR — verify a license and unlicensed activity resources
Last checked: October 16, 2026. This page is general information, not legal advice. Requirements vary by jurisdiction; the statutes and codes linked above govern, and your city or county’s building department is the authority for your address.