Yes, a Florida homeowner can pull the permit to replace their own windows. Section 489.103(7) of the Florida Statutes lets an owner act as their own contractor on a one- or two-family home they will use themselves, provided they personally sign the permit application and a disclosure statement, supervise the work on site and pass the same inspections. This guide explains who qualifies, what the disclosure statement commits you to, which documents a window permit needs, and what SmartWay supplies when you buy material only.

Last checked: October 17, 2026 · General information, not legal advice. The statute and your building department’s forms govern; ask the department before you apply.

Who qualifies

QuestionWhat s. 489.103(7) says
WhoThe owner of the property, acting as their own contractor
What buildingA one-family or two-family residence or a farm outbuilding; commercial buildings only under a cost cap
PurposeThe owner’s own occupancy or use, not offered for sale or lease
SupervisionDirect, onsite supervision by the owner of all work not done by license holders
SigningThe owner personally appears and signs the permit application
DisclosureA disclosure statement in the form the statute sets out, signed and returned
ResaleSale or lease within one year after completion creates a presumption the work was for sale or lease

Counties can add requirements. Miami-Dade County, for example, asks that the property be in a person’s name rather than a company or trust, requires proof that it is your primary residence at validation, and states the resale period on its form as 24 months from permit issuance. If your city runs its own building department, its forms are the ones that apply.

The disclosure statement, in plain language

The statute prints the statement the permitting agency hands you. It has twelve numbered points plus a warning about unlicensed contractors. These are the ones that matter for a window job:

What you acknowledgeWhat it means
You are applying under an exemptionState law requires construction by a contractor holding a state license; the exemption lets you act as your own contractor, with restrictions.
You are the responsible party of recordThe permit is in your name. Hiring a contractor who files the permit in their name moves that risk to them.
Own use onlyOne- or two-family residence (or farm outbuilding) for your own use or occupancy, not built or substantially improved for sale or lease.
Direct, onsite supervisionYou supervise the work yourself, on site.
No unlicensed contractorYou may not hire an unlicensed person to act as your contractor or to supervise workers.
Workers are your employeesAnyone working without a license works under your supervision and is your employee: tax withholding and workers’ compensation are on you.
Injury liabilityYou can be held liable for injuries to unlicensed workers, and your homeowner’s policy may not cover them.
Codes still applyThe work must comply with all applicable laws, ordinances, building codes and zoning.

One warning in the statement deserves its own line: it says it is a frequent practice of unlicensed persons to have the property owner obtain an owner-builder permit that wrongly implies the owner is providing the labor. Miami-Dade puts it more bluntly on its owner-builder page: if a contractor tells you to get an owner-builder permit, you become legally responsible for all the work done.

What the owner has to do

  1. Check the building department. City or unincorporated county; each has its own portal and forms. The county hubs for Broward, Miami-Dade and Palm Beach list the permit office for every city.
  2. Prepare the application. Proof of ownership, the signed application, the disclosure statement and the identity check the department asks for — a driver license copy, a notarized signature or another accepted verification.
  3. Attach the product approvals. A Miami-Dade NOA or Florida Product Approval for every window and door, matching the series and configuration you are installing. Our NOA guide shows how to check one.
  4. Provide the drawings or scope. Typically elevations with opening sizes, the approval numbers and the anchoring from the approval’s installation drawings. Miami-Dade asks for plans digitally signed and sealed by a design professional.
  5. Pass validation where required. Miami-Dade issues an owner-builder permit only after the owner appears, in person or virtually, to affirm they understand the disclosure statement.
  6. Record the Notice of Commencement when the job is large enough to need one, before the first inspection. The threshold and timing are in our permits and inspections guide.
  7. Schedule and pass the inspections. At least an in-progress and a final: anchors, bucks, labels, sealing and egress, checked against the approval.

Inspections: the approval is the checklist

The inspector does not grade effort. They compare the installation to the product approval: anchor type, spacing and edge distance for your wall; the buck or substrate; the permanent labels on the frame and glass; sealing. An owner-builder is held to the same drawings as a contractor. Keep the complete approval document on site, leave labels on until the final, and remember that sleeping rooms must keep a usable escape opening — see bedroom egress rules.

What SmartWay supplies for material-only buyers

On a material-only order, SmartWay supplies made-to-order impact windows and doors built to the sizes you provide. Before anything goes to the factory, a specialist checks sizes, product fit and the product approval for your exact selection; we state an approval when the document is on file for your selection, not because a product line generally carries one. Ask for the complete approval document for each product; it is what your permit application needs.

What we do not do on that path: pull your permit, measure your openings or install. The sizes you send are the sizes that get built, so measure carefully — the rough opening guide explains which number to send.

When to hire installation instead

An owner-builder permit makes sense when you, or the crew you employ and supervise, can install to the approval drawings and carry the liability. If not, the simpler path is a contractor who pulls the permit in their own name. For projects in Miami-Dade, Broward and Palm Beach: Professional installation options available. The licensed contractor responsible for work requiring licensure will be identified in the applicable proposal, contract and permit.

Questions we actually get

Can a homeowner pull a permit to install impact windows in Florida?
Yes, under the owner-builder exemption in s. 489.103(7), Florida Statutes, for a one- or two-family residence you will use or occupy yourself. You personally appear and sign the permit application and a disclosure statement, supervise the work on site, and pass the same inspections a contractor would.
Can I hire someone to install the windows on my owner-builder permit?
Only within limits. A contractor holding the right license should pull their own permit for their work. Anyone without a license who works on your owner-builder permit must work under your direct supervision as your employee, which brings tax withholding and workers’ compensation duties. You may not hire an unlicensed person to act as your contractor.
What happens if I sell the house after an owner-builder window job?
The statute says that selling or leasing within one year after completion creates a presumption that the work was done for sale or lease, which the exemption does not allow. Miami-Dade County’s owner-builder form and page state the period as 24 months from permit issuance. Read the form your building department uses.
What documents does a window permit need from an owner-builder?
Expect proof of ownership, the signed application and disclosure statement, the product approval (Miami-Dade NOA or Florida Product Approval) for every window and door, and the drawings or scope the department asks for, such as elevations with sizes and the anchoring from the approval. Miami-Dade also requires an owner-builder validation appointment before it issues the permit.
Does SmartWay pull the permit for material-only orders?