Hurricane code · Plantation · Broward County

Hurricane window code in Plantation, FL: what applies to your home

Plantation homes fall under the High-Velocity Hurricane Zone rules of the Florida Building Code, even though the city is inland. Typical homes are designed for 170 mph winds, windows need a Miami-Dade NOA or an HVHZ-approved Florida approval, and each retrofit permit needs Broward's Uniform Retrofit Window & Door Schedule.

Last checked: October 24, 2026 · General information, not engineering or legal advice. Confirm requirements for your address with the building department.

No beach, same hurricane code

Plantation has no ocean or Intracoastal frontage. It sits west of Fort Lauderdale, with Sunrise to the west and north and Davie to the south. That does not mean lighter window rules.

The code does not draw the line at the coast. It draws it at the county line. Broward and Miami-Dade are the only two Florida counties in the High-Velocity Hurricane Zone (HVHZ), and every part of Plantation is inside Broward. HVHZ provisions are generally stricter than the rest of the state.

Being inland mainly changes salt air: exposure is lower here than in beachfront cities. Wind pressure and debris rules stay the same.

The 170 mph number and what it means for a window

Section 1620.2 of the Florida Building Code sets the design wind speed for Broward County at 170 mph (3-second gust) for Risk Category II buildings, which covers typical homes. Miami-Dade, next door, uses 175 mph.

That speed is not the rating printed on a window. It is turned into a design pressure for each opening, based on its size, height and position on the house.

Because Plantation is in the HVHZ, every exterior window and door also has to resist wind-borne debris. That means impact-rated glass or an approved shutter system on each opening.

Plantation's housing age: a 1980s city

Plantation was incorporated in 1953 with fewer than 500 residents. Developer Frederick C. Peters bought about 10,000 acres along State Road 7/441 and hired architect Russell Pancoast to draw a master plan with minimum lot sizes and separate zoning districts.

Census data shows when. The median home in Plantation was built in 1984. About 65.5% of housing units were built before 1990, and about 86% before 2000. Only about 14% were built in 2000 or later.

That timing matters. Hurricane Andrew in 1992 led to the statewide Florida Building Code, first effective in 2002, which kept the stricter HVHZ rules for Broward and Miami-Dade. Most Plantation homes were built before that code existed, so their original windows were not made to today's impact and pressure standards.

Plantation housing units by decade built (ACS 2024 1-year)
BuiltHousing unitsWhat it usually means for windows
1970s8,826Built before the statewide code
1980s (largest decade)11,625Built before Hurricane Andrew and the 2002 code
1990s8,707Mostly before the 2002 code; check permit history
2000 and laterAbout 14% of all unitsBuilt under the Florida Building Code; impact glass or shutters

NOA or Florida approval: the HVHZ check most people miss

In the HVHZ, a window or door needs one of two approvals: a Miami-Dade Notice of Acceptance (NOA), or a Florida Product Approval (an FL number) whose Limits of Use say it is approved for use in the HVHZ.

Not every Florida Product Approval qualifies. A product approved for the rest of Florida may not be approved for the HVHZ. Check the record on floridabuilding.org before you accept a quote.

HVHZ products are tested to three protocols: TAS 201 (large missile impact), TAS 202 (static pressure) and TAS 203 (cyclic loading).

  • Ask for the NOA or FL number for every product in the quote.
  • Confirm the approval says HVHZ, not just Florida.
  • Check that each opening's size is covered by the approval.
  • Check that the approved pressure is equal to or higher than the required design pressure for that opening.

Broward's retrofit schedule: one line per opening

Broward County adds its own paperwork step. Every window and door retrofit permit application in the county must include the Broward County Uniform Retrofit Window & Door Schedule, set by Board of Rules and Appeals Policy 20-01 (adopted July 1, 2020, revised April 11, 2024).

The schedule lists each opening on the house with its ID, product approval number, approved pressure rating, required design pressure, size, wind zone, impact glazing, shutters and mullions. It ties the 170 mph code to the actual windows on your house.

How the City of Plantation handles window permits

Window and door permits in Plantation are issued by the City of Plantation Department of Building Safety. The main line is 954-797-2765, the inspection line is 954-678-2632, and the email is Helpmebuilding@plantation.org.

Applications, inspection scheduling, inspection results and permit status all run through the city's Citizen Access portal. Only contractors holding the proper state license, or accounts registered and activated by Building Safety, can submit or schedule. Registration needs a notarized Web User Declaration and takes about 1 to 2 business days.

  1. Gather product approvals. The city's Permit Submittal Checklist lists windows, doors, garage doors and shutters under product approvals. If a product has no product approval, a Broward County Product Approval submittal is required.
  2. Complete the retrofit schedule. Fill out the Broward Uniform Retrofit Window & Door Schedule with every opening, approval number and design pressure.
  3. Consider Same Day Permit Services. For existing single-family homes only, Plantation offers same-day window/door and shutter permits. Packages go through Citizen Access on Wednesdays, 6 to 9 a.m., and must be standalone with every item on the city's Window/Door or Shutters Checklist.
  4. Record the Notice of Commencement. When the direct contract is above the threshold in Florida's lien law (s. 713.135 F.S., raised in 2023), a clerk-issued copy of a recorded Notice of Commencement must be filed before the first inspection. Plantation's 2019 checklist still shows the older threshold.
  5. Schedule inspections in Citizen Access. Request inspections through the portal or the inspection line, and ask which inspections your permit needs.
  6. Document it for insurance. After the work, a wind mitigation inspection on form OIR-B1-1802 can document the new opening protection for your insurer.

Doing it yourself: Plantation's owner-builder limits

Plantation allows owner-builder permits only for the owner's primary residence or homestead. Condos are not eligible. The owner must show proof of ownership, meet with the division chief for each trade and personally supervise the work on site.

The city's affidavit warns that hiring workers without a contractor license can make the owner liable for their injuries. Contractors must register with the city and file liability and workers' compensation certificates.

Condos, townhomes and HOA rules

Plantation is not only single-family homes. About 48% of housing units are single-family detached, about 8% are townhomes and other attached homes, and about 32% are in buildings with 10 or more units. About 18% are in buildings of 50 or more units.

Condo and co-op buildings three or more stories tall fall under Florida's milestone inspection law (s. 553.899 F.S.). The first inspection is due by December 31 of the year the building turns 30, then every 10 years. Broward's own program (BORA Policy 05-05) also inspects non-exempt buildings 30 years or older; houses, duplexes and fee-simple townhouses are exempt. If you own a unit, ask the association about its window rules before choosing a product.

Many neighborhoods also have their own architectural review. Plantation Lakes, for example, publishes ARC Design Guidelines that govern exterior changes. HOA approval is separate from the city permit, so get it first.

Flood risk here is rain, not surge

About 10% of Plantation's land is in a FEMA flood zone. The city says heavy rain from hurricanes and tropical storms is its greatest flood risk. Updated FEMA flood maps for Broward County took effect July 31, 2024, so a zone you checked years ago may have changed.

Much of the city drains through the Old Plantation Water Control District, an independent district created in 1946 that runs about 36 miles of waterways and four major pumping stations.

To check your lot, use Broward County's flood map, print a free FEMA FIRMette, or ask the City Engineering Department (954-797-2282) for a map determination letter.

What differs from one Plantation neighborhood to the next

  • Plantation Acres (33323): large lots, many around one acre. Spread-out homes can mean a long retrofit schedule.
  • East side (33317), including Plantation Isles, Plantation Gardens, Melrose Park and Country Club Estates: check whether your windows are original.
  • Mirror Lake and Lauderdale West (33322 and 33324): in an association or multi-unit building, its rules come before the city permit.

A code edition change is coming

Permits in Plantation today are reviewed under the 8th Edition (2023) Florida Building Code, in effect since December 31, 2023. The 9th Edition (2026) is scheduled to take effect December 31, 2026, with final adoption steps still pending in October 2026. Permits applied for before the effective date generally stay under the 8th Edition.

Planning near that date? Ask which edition applies. To compare options, send your measurements and opening list and get a written quote, or call (754) 303-7130 with questions.

Plantation questions

Plantation is inland. Do I still need impact windows?
Yes, if you replace exterior windows. Plantation is in Broward County, which is in the High-Velocity Hurricane Zone no matter how far you are from the beach. New windows and doors must resist wind-borne debris, so each opening needs impact-rated glass or an approved shutter system.
What design wind speed applies to a house in Plantation?
Florida Building Code Section 1620.2 sets 170 mph (3-second gust) for Broward County Risk Category II buildings, which covers typical homes. Each window's required design pressure is then worked out from that speed and the opening's size and location on the house.
Can I use a window with a Florida Product Approval in Plantation?
Only if the approval's Limits of Use say it is approved for the HVHZ. A Miami-Dade NOA also works. Some Florida approvals cover the rest of the state but not the HVHZ, so check the record on floridabuilding.org before you sign.
Can I get a same-day window permit in Plantation?
Possibly. Plantation's Same Day Permit Services cover window/door and shutter permits for existing single-family homes only. Submit through Citizen Access on Wednesdays between 6 a.m. and 9 a.m., up to 5 submittals per applicant, with every item on the city's Window/Door Checklist.
Can I pull my own window permit for a Plantation condo?
No. Plantation allows owner-builder permits only for the owner's primary residence or homestead, and not for condos. For a single-family homestead, you must prove ownership, meet with the division chief for each trade and personally supervise the work.
My Plantation home was built in the 1980s. Does that matter?
It does. The 1980s is Plantation's largest building decade, and those homes predate Hurricane Andrew and the 2002 statewide code. Original windows were not made to today's HVHZ impact and pressure tests, so replacements are permitted under current rules.